Industrial WWTP Sep 2025 – Oct 2025 Saudi Aramco

H₂S Seawater Treatment — 42" MJTNG-1 Pipeline

A higher-capacity sulfide-treatment system for the seawater used to flood the 42-inch MJTNG-1 pipeline — 1,000 m³/hr, 50,000 m³ total — with a full on-site lab monitoring sulfide throughout.

H₂S Seawater Treatment — 42" MJTNG-1 Pipeline
Capacity
1,000 m³/hr (50,000 m³ total)
Technology
Dosing Pumps → Sulfide Scavenger → Chemical Injection → Activated Carbon
Timeline
Sep 2025 – Oct 2025
Project type
Integrated dosing system + on-site lab
Executive summary

An integrated high-capacity dosing system for sulphide treatment of seawater used to flood the 42" MJTNG-1 pipeline, processing 50,000 m³ at 1,000 m³/hr with a full on-site laboratory for continuous sulphide monitoring throughout the flooding procedure.

FK & Partner Co. and Water Technology Company (W-Tech) supplied an integrated sulfide-scavenger dosing system with activated-carbon odour control, processing 50,000 m³ at 1,000 m³/hr, and ran a full-scale laboratory to monitor sulfide levels during the flooding procedure.

The challenge

A larger 42-inch line flood needs sulfide dosing at double the flow of phase 1, with continuous verification that levels stay controlled throughout the operation.

Site & process constraints
  • 42-inch line flooding
  • 1,000 m³/hr — double phase 1
  • Continuous sulfide verification
Engineering approach

A treatment train sequenced to the contaminants.

Dosing Pumps → Sulfide Scavenger → Chemical Injection → Activated Carbon

Dosing pumps inject sulfide scavenger into the seawater stream; activated carbon controls odour; and a full-scale on-site laboratory verifies sulfide levels in real time throughout the flooding procedure.

On-site lab: real-time sulfide monitoring de-risks a time-critical pipeline operation.
Technical specifications
Equipment & key parameters (from the project scope)
Equipment / parameterApplication / value
Dosing PumpsChemical injection
Sulfide ScavengerSulphide treatment
Flow rate1,000 m³/hr
Total volume50,000 m³
Capacity1,000 m³/hr (50,000 m³ total)
Project typeIntegrated dosing system + on-site lab
Implementation
Sep 2025
Integrated dosing system mobilised.
Oct 2025
50,000 m³ treated during flooding.
Results & outcomes

High-capacity dosing at 1,000 m³/hr

On-site lab for continuous sulphide monitoring

Activated carbon for odour control

Verified post-commissioning performance figures (achieved effluent, throughput, uptime) to be confirmed — see CONTENT_GAPS.