  Client: Saudi Aramco  ·  Oct 2024 - Oct 2025

Wastewater Treatment Facilities for SDS 2 — Jizan Refinery

About Jizan Refinery

Jizan Refinery, on the Red Sea coast in southwest Saudi Arabia, is one of Saudi Aramco's newest facilities with ~400,000 barrels/day processing capacity. It produces clean fuels to international standards with hydrotreating, hydrocracking, and sulfur recovery units.

Basins A & B Wastewater Treatment — SDS 2

Supply, installation, and operation of a treatment system to process pretreated wastewater from Basins A and B to meet existing Water Treatment Plant inflow quality requirements. System handles up to 100 m3/hr with oil-water separator, DAF, sulfide scavenger, and activated carbon. Total volume: 275,000 m3.

Scope of Work

IE-Consult provided complete design, engineering solution, and project management.

FK & Partner Co. & W-Tech Co. supplied and installed oil-water separator (100 m3/hr, up to 10,000 ppm oil), DAF unit, sulfide scavenger dosing, and activated carbon units.

All supporting equipment, pipelines, and instrumentation supplied and installed as a complete system.

Jizan Refinery — WWT Facilities SDS 2
 Equipment Specifications
Equipment / ParameterApplication / Value
Cyclone Oil-Water Separator100 m3/hr — oil droplet separation
DAFCoagulation / Floatation
MM FilterTSS removal
Sulfide Scavenger Dosing SystemSulfide treatment of wastewater
Activated CarbonOdor control — H2S capture
Total Volume275,000 m3
Capabilities

Treatment Process Capabilities

 High-flow cyclone oil-water separation at 100 m3/hr
 DAF for coagulation and suspended solids removal
 Multi-media filtration for final TSS polishing
 Sulfide scavenger dosing for chemical neutralization
 Activated carbon for H2S odor control
 System meeting existing Jizan Water Treatment Plant inflow specifications
Jizan Refinery — WWT Facilities SDS 2