Get in Touch
  Client: Saudi Aramco  ·  Oct 2024 - Oct 2025

Wastewater Treatment Facilities for SDS 1 — Jizan Refinery

About Jizan Refinery

Jizan Refinery, on the Red Sea coast in southwest Saudi Arabia, is one of Saudi Aramco's newest facilities with ~400,000 barrels/day capacity of Arabian Heavy crude. It includes hydrotreating, hydrocracking, and sulfur recovery units producing clean fuels to international standards.

Sulfide Removal — Tank D-0101

Supply, installation, and operation of a treatment facility to remove sulfides from ~30,000 m3 of accumulated sour water in Tank D-0101 at Jizan Refinery. Target: reduce sulfide concentration from ~8,000 ppm to less than 1 ppm, meeting Jazan WWTP discharge requirements.

Scope of Work

IE-Consult provided complete design, engineering solution, and project management.

FK & Partner Co. & W-Tech Co. supplied and installed oil-water separator (10,000 ppm oil, 20 m3/hr), DAF unit, sulfide scavenger dosing system, and activated carbon units for H2S capture.

All pipelines, instrumentation, and supporting equipment supplied and installed as a complete system.

Jizan Refinery — WWT Facilities SDS 1
 Equipment Specifications
Equipment / ParameterApplication / Value
Cyclone Oil-Water SeparatorSeparate oil droplets from water phase
DAFCoagulation / Floatation
MM FilterTSS removal
Sulfide Scavenger Dosing SystemSulfide treatment of wastewater
Activated CarbonOdor control — H2S capture
Target Sulfide Level<1 ppm (from ~8,000 ppm)
Total Volume30,000 m3
Capabilities

Treatment Process Capabilities

 Cyclone oil-water separation for oily sour water pre-treatment
 DAF for suspended solids and residual oil removal
 Multi-media filtration for TSS polishing
 Sulfide scavenger dosing for sulfide neutralization to <1 ppm
 Activated carbon for H2S odor control and gas capture
 System meeting Jazan WWTP inflow quality requirements